|
City of York
Council
|
Committee Minutes
|
|
MEETING
|
Fulford and Heslington
Ward Committee
|
|
DATE
|
24 November
2025
|
|
PRESENT
|
COUNCILLORS
|
|
APOLOGIES
|
COUNCILLORS
|
|
|
|
<AI1>
1.
Drop
In/Ward Surgery
</AI1>
<AI2>
2.
Introductions
1. MAIN
MEETING – WELCOME AND INTRODUCTIONS (18:30)
The meeting was chaired by Councillor Kate
Ravilious who welcomed everyone and set out the housekeeping rules
and reminded residents that the meeting was non-political.
</AI2>
<AI3>
3.
Germany
Beck Pumping Station
2. Germany
Beck Pumping Station – Mark Henderson CYC Flood
Manager
Project
Overview:
- Mark Henderson introduced himself and
provided an update on the Germany Beck flood management project. He
welcomed questions during or after the presentation.
Location &
Infrastructure:
- Germany Beck and the associated pumping
station were highlighted. Downstream impacts affect the A19 and
local SSSI areas.
Flood Impacts:
- High water levels in Germany Beck can back
up, causing flooding at Fordlands Road and Fordlands Crescent.
- In severe cases, temporary infrastructure
like a scaffolded bridge is required to maintain access.
- Surface water drainage from residential areas
(e.g., Fordlands Estate) contributes to local flooding, with
approximately 300+ properties affected.
- Historical context: Around 20–23
properties were flooded in 2015.
Scheme
Justification:
- Main drivers: prevent road blockages at
Fordlands Road, reduce residential flooding at Fordlands Crescent,
and manage tunnel drain overflow.
- Economic and community benefits: preventing
flooding protects homes, ensures road accessibility (A19 carries
~16,000 vehicles/day), and supports broader local economic
impacts.
Funding:
- Central government and City of York Council
are co-funding the scheme based on the business case demonstrating
flood risk reduction and economic benefits.
Pumping Station
Function:
- The pumping station will draw water from
Germany Beck when high water levels cause hydraulic locking at the
Ings.
- Water will be pumped through an offline
system into a wet well and then through a new culvert under the A19
to manage flow.
- Downstream risk is minimal; modelling shows
the pumped volume is negligible relative to the total water
body.
Project Timeline
& Procurement:
- Specialist contractor procurement planned for
April–May next year; contract to be approved by August.
- Site mobilisation and planning condition
discharges will occur before work starts.
- Construction is expected to begin in autumn
next year.
Budget:
- Indicative cost: ~£4.5 million,
including 25–30% contingency. Final cost depends on market
responses.
Sequence of
Works:
- Key elements: pumping station, kiosk/pump
panel, culvert, downstream headwall, and structural changes to
upstream/downstream areas.
- Work may be phased; exact sequencing will be
determined once the contractor is appointed.
Temporary Access
& Storage:
- Parts of the park will be temporarily
cordoned off for access, equipment storage, and work along the bank
and parish field.
- Access will be via Fordlands Road. Temporary
disruptions are expected, but benefits of the project are expected
to outweigh short-term inconveniences.
Project
Timeline:
- Work expected to start in autumn 2026
(following mobilisation).
- Duration estimated at around one year,
slightly longer than the original 64-week business case
projection.
- Design refinements may occur once the
contractor begins work, similar to adjustments made after an
architect hands over to a builder.
- Project completion anticipated by autumn
2027.
Constraints &
Impacts:
- Key considerations include ecology,
landscape, archaeology, and A19 impacts.
- Ecological protections:
-
- Areas of ecological importance (SSSI/triple
S) identified downstream of A19.
- Pumping station designed to be eel-friendly,
using slower, larger impellers (similar to an Archimedes screw) to
allow safe passage of eels.
- Water vole surveys conducted in September;
further surveys planned in April.
Ecological Surveys
& Protections:
- Spring 2025 surveys planned for water voles;
mitigation measures and licenses required if present.
- No signs of otters; nesting birds will be
protected.
- Tree management: some trees may be removed,
others retained or replaced, with protections for roots.
- Invasive species (Himalayan balsam,
waterweed) will be carefully managed to prevent spread.
- Additional ecological surveys needed: bats,
trees, and habitats, as previous surveys (2021) are now
outdated.
- Construction will follow detailed
Environmental Management Plans and method statements to minimise
ecological impact.
Archaeology:
- Work with local and county archaeologists to
manage potential archaeological finds, including Battle of Fulford
area.
- Excavation for the pumping station may
uncover historical materials, which will be sifted with volunteer
involvement.
- Archaeological mitigation and recording will
be integrated into the construction process.
Q&A –
Germany Beck Flood Management
Archaeology &
Project Timelines:
- Significant finds during excavation will be
removed and investigated but will not delay construction.
Archaeologists will work alongside contractors.
A19 &
Construction Impacts:
- Options for culvert construction under the
A19 include partial road closure or thrust boring;
final approach pending geotechnical studies and traffic
modelling.
- Work involves significant construction due to
peat layers and foundation requirements.
Design &
Environmental Considerations:
- Pumping station design largely fixed, with
minor tweaks possible for eel-friendly pumps and sluices.
- Landscaping and tree replacement plans in
place; temporary use of the playing field will not affect newly
planted areas.
Flooding &
Access Concerns:
- Concerns raised about pedestrian and vehicle
access during floods, particularly for carers and emergency
access.
- Current interim measures (scaffold bridges,
pumps) will remain until pumping station is operational.
- Possibility of additional temporary
structures or increased pump capacity to manage water levels is
being explored.
Tunnel Drain &
Sewer System:
- Pumping station will maintain free flow in
Tunnel Drain, preventing backflow and flooding of properties.
- Some foul water misconnections may exist;
issue to be investigated with Yorkshire Water.
- Maintenance responsibility for culverted
sections is complex; currently managed by Internal Drainage Board,
with cost and liability considerations.
Funding & Legacy
Issues:
- Project funded by City of York Council and
central government; efforts ongoing to minimise cost to
taxpayers.
- Historical development (e.g., Persimmon
Homes) contributed to some existing flood issues; responsibility
outside development boundaries is limited.
- Environmental improvements will be made where
the pumping station impacts SSSI areas, but no wider remediation
beyond the project area.
Additional
Notes:
- Residents’ concerns about SSSI
mitigation, flood season impacts, and temporary access
acknowledged; further updates to be communicated as information
becomes available.
- Mark Henderson emphasised transparency,
cost-effectiveness, and collaboration with other agencies.
</AI3>
<AI4>
4.
Fulford
Parish Field Consultation Update
3. Fulford
Parish Field – Abigail Gaines – MakeSpace York
Parish Fields
Consultation – Feedback Summary
- Purpose: Provide an update on the second
phase of community engagement regarding the Parish Fields and the
adjoining Persimmon Field.
Current Use of the
Area:
- Parish Field: children’s play
equipment, large grass areas used for football pitches and annual
events (e.g., Fulford Show), and a sports pavilion.
- Persimmon Field: currently undeveloped; may
be handed over to the parish council if proposals proceed.
Background:
- Section 106 funds from Persimmon Homes’
Germany Beck development are being considered for
improvements.
- First consultation (2022) engaged 341
residents, mostly sports-focused; some groups (e.g., older
residents, teenagers, those without internet access) were
underrepresented.
- Top option previously was improving football
pitches, sports pavilion, and adding paths, nature, and gardening
spaces.
Second Consultation
(2025):
- Aim: reach wider community, include informal/
formal sport, active lifestyles, and broader usage ideas.
- Surveys:
-
- Online survey: 394 responses.
- School survey (Year 9 and others): 252
responses.
- Paper surveys also available.
- Engagement sessions included:
-
- Drop-ins, coffee mornings, and informal
discussions at Fulford Social Hall, Library, St. Oswald’s
Church Hall, Fulford Show.
- Workshops with Fulford students (including
older girls).
- Targeted focus groups at assisted housing
(United Response, Delwood) and Ouse View Care Home.
- Engagement with community champions to
capture diverse perspectives.
</AI4>
<TRAILER_SECTION>
,
Chair
[The meeting
started at 6.00 pm
and finished at 8.00 pm].
</TRAILER_SECTION>
<LAYOUT_SECTION>
1.FIELD_TITLE
FIELD_SUMMARY
</LAYOUT_SECTION>
<TITLE_ONLY_LAYOUT_SECTION>
2.FIELD_TITLE
</TITLE_ONLY_LAYOUT_SECTION>
<HEADING_LAYOUT_SECTION>
FIELD_TITLE
</HEADING_LAYOUT_SECTION>
<TITLED_COMMENT_LAYOUT_SECTION>
FIELD_TITLE
</
TITLED_COMMENT_LAYOUT_SECTION>
<COMMENT_LAYOUT_SECTION>
FIELD_SUMMARY
</
COMMENT_LAYOUT_SECTION>
<SUBNUMBER_LAYOUT_SECTION>
2.1
FIELD_TITLE
FIELD_SUMMARY
</SUBNUMBER_LAYOUT_SECTION>
<TITLE_ONLY_SUBNUMBER_LAYOUT_SECTION>
2.2
FIELD_TITLE
</TITLE_ONLY_SUBNUMBER_LAYOUT_SECTION>